Installation and pre-commissioning of all refinery facilities and Main Pipe rack including:
Earthworks: 244,000 cubic meters
Concreting: 47,000 cubic meters
Installation of steel structure: 11,000 tons
Installation of equipment: 3772 tons
Piping and insulation: 702,000 inches in diameter
Electricity and instrumentation: 2000 tons + 1000 km of cabling
Painting: 169,000 square meters